Starting on the second float half

Categories: Bulkheads Floats

Had a lot of positive feelings from yesterday. It’s nice to look up at the ceiling and see the first of four float halves completed. We started on the second float half today.

Dad spent most of the afternoon cleaning and starting to plank the second half

466

While I infused the middle bulkhead and the forward beam bulkhead

473

Put a pretty good dent in things and left it here for this evening

485

At this rate we’re thinking the second float half should be completed next weekend or the beginning of the weekend-after. Then we reverse the frames and start doing the opposite sides and building the decks.

Time spent: 10 hours